Historical Schedule Adherence in Amazon Connect
This section describes the values used when calculating Historical Schedule Adherence.
Adherence
Percentage of time that an agent correctly follows their schedule. This is measured by tracking if an agent is in an Available agent status when they should be in productive state. This percentage is calculated as follows:
Adherence % = ((Total Adherent Minutes)/ Total Scheduled Adherence Minutes)
An agent is considered adherent if the agent is in an Available Status, when the shift activity is Productive, or if the agent is in Non-Productive Status (i.e Custom Status), when the shift activity is Non-Productive. Otherwise the agent is considered non-adherent. This means that if a shift activity is called Lunch but marked as productive, the agent is considered adherent if they are in the Available agent status.
-
Type: String
-
Min value: 0.00%
-
Max value: 100.00%
-
Category: Agent activity-driven metric
Note
Anytime you change the schedule, Schedule Adherence is re-calculated up to 30 days in the past from the current date (not the date of the schedule), if schedules are changed.
Adherent time
Total time an agent was in an Available status when their shift activity is productive or was is in non-productive status when the shift activity is non-productive.
-
Type: String (hh:mm:ss)
-
Category: Agent activity-driven metric
Non-Adherent time
Total time an agent was not in an Available status when their shift activity is productive or not in a non-productive status when their shift activity is non-productive.
-
Type: String (hh:mm:ss)
-
Category: Agent activity-driven metric
Scheduled time
Total time an agent was scheduled (either for productive or non-productive
time) and Adherence for those shifts were set to Yes
.
-
Type: String (hh:mm:ss)
-
Category: Agent activity-driven metric